About the project
33KV Mukono–Katosi transmission line.
Project description
Surveying and setting out the proposed 33KV powerline route for transmission to the National Water & Sewerage Corporation (NWSC) plant. The route length was 40 km from UETCL Mukono Station.
| Item | Detail |
|---|---|
| Voltage | 33KV |
| Route length | 40 km |
| Start point | UETCL Mukono Station |
| End point | NWSC Katosi plant |