Scoping Study and Investment Package for Energy Access and Resilience for Northern Uganda (EARN)

Client
NTU International A/S
Location
31 districts and cities across Northern Uganda
Period
Apr 2026 – May 2027
Funder
European Union
Status & sector

Ongoing | Energy

A pre-feasibility and feasibility study for a €100 million investment package to widen access to electricity in rural and peri-urban Northern Uganda, for potential co-financing by the EIB.

Project vehicle fleet on site — COGO field photo

About the project

Scoping study and investment package for Energy Access and Resilience for Northern Uganda (EARN).

Project description

The main task is to develop a pre-feasibility study and then a feasibility study of a 100-million Euro investment package to increase access to electricity in rural and peri-urban areas in Northern Uganda, to be considered for potential co-financing by the EIB. It consists of four components:

  1. Grid expansion and connectivity for 1,470 km of Medium Voltage powerline and 3,000 km of Low Voltage powerlines.
  2. Strengthening the existing distribution network.
  3. Productive use of energy.
  4. Last-mile consumer connections.

Project location

Adjumani, Agago, Alebtong, Amolatar, Amudat, Amuru, Apac, Dokolo, Gulu, Gulu City, Kaabong, Kitgum, Kole, Kotido, Kwania, Lamwo, Lira, Lira City, Madi Okollo, Moroto, Nabilatuk, Nakapiripirit, Napak, Nebbi, Nwoya, Omoro, Otuke, Oyam, Pader, Pakwach and Zombo.

Component Scope
Grid expansion & connectivity 1,470 km MV and 3,000 km LV powerlines
Distribution network Strengthening the existing network
Productive use of energy Energy for productive activities
Last-mile connections Consumer connections